Construction Schedule

Draft v1

Fab 4 Expansion57 activities · 65 dependencies · 5 milestones

Total Activities
57
In Progress
9
Complete
9
Milestones
5
Dependencies
65
ID
Activity Name
Start
Finish
Dur
Design Phase5
DES-001
Fab 4 Detailed Design Complete
1/5
0d
DES-002
Cleanroom Layout Finalization
1/5
2/13
30d
DES-003
CUB Utility Design Package
1/5
2/6
25d
DES-004
Electrical Distribution Design
1/12
2/20
30d
DES-005
Process Piping Design
2/18
4/7
35d
Procurement27
CUB-P01
Chiller Submittal Prep
2/10
2/17
5d
CUB-P02
Chiller Submittal Review
2/18
3/3
10d
CUB-P03
Chiller PO Award
3/4
3/10
5d
CUB-P04
Chiller Fabrication
3/11
5/19
50d
CUB-P05
Chiller FAT & Ship
5/20
6/10
15d
CUB-P06
Chiller Receiving
6/11
6/15
3d
CUB-P07
Compressor Submittal & PO
2/10
3/10
20d
CUB-P08
Compressor Fabrication
3/11
5/5
40d
CUB-P09
Compressor FAT & Ship
5/6
5/27
15d
CUB-P10
UPW System Procurement
2/10
5/12
65d
CUB-P11
N2 Generator Procurement
2/10
4/28
55d
EUV-P01
EUV Submittal Preparation
2/18
3/3
10d
EUV-P02
EUV Submittal Review
3/4
3/24
15d
EUV-P03
EUV PO Award
3/25
3/31
5d
EUV-P04
EUV Fabrication (ASML)
4/1
9/25
125d
EUV-P05
EUV FAT (Veldhoven)
9/28
10/9
10d
EUV-P06
EUV Shipping & Logistics
10/12
11/6
20d
EUV-P07
EUV Receiving & Inspection
11/9
11/13
5d
CMP-P01
CMP Submittal & Review
2/18
3/17
20d
CMP-P02
CMP PO Award
3/18
3/24
5d
CMP-P03
CMP Fabrication (Ebara)
3/25
7/9
75d
CMP-P04
CMP FAT & Ship
7/10
8/6
20d
CMP-P05
CMP Receiving
8/7
8/11
3d
CVD-P01
CVD Submittal & Review
2/18
3/17
20d
CVD-P02
CVD PO & Fabrication
3/18
7/16
85d
CVD-P03
CVD FAT & Delivery
7/17
8/13
20d
ETCH-P01
Etch Procurement (Lam)
2/23
7/17
105d
Installation21
CUB-I01
Chiller Foundation & Set
6/16
7/1
12d
CUB-I02
Chiller Mech/Elec/Piping
7/2
7/23
15d
CUB-I03
Chiller Startup & Commission
7/24
8/6
10d
CUB-I04
Compressor Install & Connect
5/28
6/24
20d
CUB-I05
CDA System Startup
6/25
7/9
10d
CUB-I06
UPW System Install
5/13
6/24
30d
CUB-I07
UPW Qualify & Commission
6/25
7/16
15d
CUB-I08
N2 Generator Install & Startup
4/29
5/27
20d
EUV-I01
EUV Site Prep & Foundation
8/3
9/4
25d
EUV-I02
EUV Equipment Set & Rigging
11/16
12/1
10d
EUV-I03
EUV Mechanical Connections
12/2
12/22
15d
EUV-I04
EUV Electrical Connections
12/23
1/6
10d
EUV-I05
EUV Utility Hookup & Test
1/7
1/20
10d
EUV-I06
EUV Startup & SAT
1/21
2/10
15d
CMP-I01
CMP Site Prep
7/31
8/13
10d
CMP-I02
CMP Equipment Set
8/14
8/24
7d
CMP-I03
CMP Connect & Startup
8/25
9/15
15d
CVD-I01
CVD Site Prep
8/14
8/27
10d
CVD-I02
CVD Install & Connect
8/28
9/25
20d
CVD-I03
CVD Startup & Qualify
9/28
10/16
15d
ETCH-I01
Etch Install & Startup
7/31
9/11
30d
Program Milestones4
MS-001
CUB Utilities Operational
8/7
0d
MS-002
Equipment Delivery Complete
11/16
0d
MS-003
Cleanroom Turnover
7/31
0d
MS-004
First Wafer Out
2/11
0d
January 2026February 2026March 2026April 2026May 2026June 2026July 2026August 2026September 2026October 2026November 2026December 2026January 2027February 2027March 2027April 2027May 2027June 20271/51/121/191/262/22/92/162/233/23/93/163/233/304/64/134/204/275/45/115/185/256/16/86/156/226/297/67/137/207/278/38/108/178/248/319/79/149/219/2810/510/1210/1910/2611/211/911/1611/2311/3012/712/1412/2112/281/41/111/181/252/12/82/152/223/13/83/153/223/294/54/124/194/265/35/105/175/245/316/76/146/216/28Fab 4 Detailed Design CompleteCleanroom Layout Final…CUB Utility Design…Electrical Distributio…Process Piping DesignChiller FabricationChiller FA…Compressor Subm…Compressor FabricationCompressor…UPW System ProcurementN2 Generator ProcurementEUV Submit…EUV Fabrication (ASML)EUV Shipping …CMP Submittal …CMP Fabrication (Ebara)CMP FAT & ShipCVD Submittal …CVD PO & FabricationCVD FAT & Deli…Etch Procurement (Lam)Chiller Me…Compressor Ins…UPW System InstallUPW Qualif…N2 Generator In…EUV Site Prep & Fo…EUV Mechan…EUV Startu…CMP Connec…CVD Install & C…CVD Star…Etch Install & StartupCUB Utilities OperationalEquipment Delivery CompleteCleanroom TurnoverFirst Wafer Out

Streamline AI

Project assistant

How can I help?

Ask me to query equipment data, generate schedules, or analyze your project.

Press Ctrl+K to toggle